Connecting a plot to utilities – find out with us how to meet all the conditions for utility connections
Connecting utilities to a newly built house is an essential step that gives you access to the necessary services, such as water, sewerage, electricity and gas.
(you can read about the others in a separate article: Building a house – 10 official matters you need to take care of).
Each of these networks requires you to go through the relevant procedures and obtain technical conditions from the appropriate providers.
Before you start connecting your plot to utilities, it is worth familiarising yourself with the current regulations on project preparation and the technical conditions for connections. On the website of the General Office of Building Control (GUNB) you will find up-to-date information on building law and the interpretation of regulations.
Every investor planning to build a house should apply to the network operators for connection conditions. You will also find detailed information on the procedures and required documents on the official government website 👉 How to obtain connection conditions.

Here is a brief overview of the procedures for connecting to each network:
Connecting to the water supply network
- Application for connection conditions: the investor submits an application to the local water company for the technical conditions of connection. The application should include details of the plot’s location, the expected water demand and a description of the project.
- Technical conditions: once the application has been submitted, the water company issues technical conditions specifying how and where the connection to the water network will be made, the technical requirements and the timescales.
- Connection design: on the basis of the conditions received, the investor or designer prepares a design for the water connection, which must be approved by the water company.
- Building the connection: once the design has been approved and consent for the works obtained, the investor can go ahead with the connection. The works may be carried out by the water company or by an authorised contractor.
- Technical acceptance: once the connection is complete, a technical acceptance inspection is carried out, followed by the formal connection to the water network.

Connecting to the sewerage network
- Application for connection conditions: as with the water network, the investor submits an application to the sewerage company for the technical conditions of connection.
- Technical conditions: the company issues conditions specifying the point of connection to the sewerage network, the requirements for pipe diameter and falls, and how waste water is to be discharged.
- Connection design: on the basis of the conditions received, a design for the sewer connection is prepared, which must be approved by the sewerage company.
- Building the connection: the sewer connection is built in accordance with the design and technical conditions, once all the necessary permits have been obtained.
- Technical acceptance: when the works are complete, a technical acceptance inspection of the connection is carried out to confirm that it complies with the design and regulations.
Connecting to the electricity grid
- Application for connection conditions: the investor submits an application to the distribution network operator for connection conditions, providing information on the expected electricity demand and the anticipated connection capacity.
- Technical conditions: the operator issues technical conditions specifying how the building will be connected to the grid, where the electricity meter will be installed and the requirements for the electrical installation.
- Connection agreement: once the conditions have been issued, the investor signs a connection agreement with the operator, setting out the connection costs and timescales.
- Building the connection: the operator or an authorised contractor builds the connection in line with the technical conditions and the connection agreement.
- Meter installation and connection: once the works are complete, the electricity meter is fitted and the building is connected to the grid.
Connecting to the gas network
- Application for connection conditions: the investor submits an application to the gas supplier for connection conditions, stating the expected gas consumption and the type of gas appliances to be installed in the building.
- Technical conditions: the gas supplier issues technical conditions setting out how the connection to the gas network will be made, the technical requirements for the gas installation and where the gas meter will be installed.
- Connection agreement: once the conditions have been received, the investor signs a connection agreement with the gas supplier, setting out the connection costs and timescales.
- Gas connection design: on the basis of the technical conditions, a design for the gas connection is prepared, which must be approved by the gas supplier.
- Building the connection: the gas connection is built in accordance with the design and technical conditions, once the required permits have been obtained.
- Technical acceptance and gas commissioning: when the works are complete, a technical acceptance inspection is carried out, after which the meter is fitted and the gas supply is switched on.

In summary, connecting to the water, sewerage, electricity and gas networks are processes that require close cooperation with the relevant utility providers. The key is obtaining the technical conditions, which set out the requirements and how the connections are to be made. Well-planned and properly executed connections ensure not only compliance with regulations, but also comfort and safety in your new home.
Want to better understand the technical options for bringing utilities to your plot? On Murator.pl you will find practical advice and examples of solutions used in different parts of the country.
And if you need practical help from someone with experience – get in touch with us ->